Successful Ignition and Commissioning Production of Guizhou Huangping Jianfeng Project
Release time:
2020-08-03 14:15
Source:
At 9:58 a.m. on August 3, 2020, the 4500t/d clinker new dry process cement production line of Guizhou Huangping Jianfeng Cement Co., Ltd., constructed by Nanjing Kisen Cement Electromechanical Equipment Installation Co., Ltd., was successfully ignited with the fire from Hubei Daye Jianfeng Cement Co., Ltd.
At 1:18 p.m. on Aug. 11th, the temperature rising of the burning system was done. The burning system also finished the first ignition, material feeding and commissioning production.

During the construction of this project, Kisen has carried forward the fine tradition and fighting spirit of daring to win tough battles and delivering high-quality projects. Kisen has mobilized skilled construction teams and advanced machinery and equipment, and developed high degree of responsibility, power, profit and efficiency. The unified construction management team has overcome the impact of the covid-19 pandemic and achieved the established ignition target safely and with high quality. It has been highly recognized by the managers of Jianfeng Group and laid a solid foundation for the following cooperation between Kisen and Jianfeng Cement.