Kiln Outlet Steel Structure Building of Wannianqing Project Successfully Capped
Release time:
2020-05-08 14:12
Source:
At 16:18 on May 8, 2020, the kiln outlet building of Jiangxi Wannianqing Cement Plant’s 2*5100T/D clinker cement production line upgrade and environmental protection relocation project was successfully capped.
This is a key project in Jiangxi Province. Our installation team began to be mobilized to the site from the beginning of March this year and have actively overcome the COVID-19 epidemic in March and the rainy season in April. We’ve also overcome the daily cross-work between the steel structure installation team and civil contractor. Under the premise of ensuring safety and quality, the building is successfully capped.
The smooth capping of the building has won the full affirmation and trust of the owner and project consultant company of our company and our project team. It also created a good beginning for the project in October and won more time for the following work of this project. The project management team will also continue to overcome difficulties and carry forward Kisen spirit to achieve the final completion of this project!