(Summary description)2018 is a year of fruitful harvest for the Malaysia project! With the careful preparation of the company's managers and departments, especially the high recognition and full support of the Malaysian Lafarge team headed by Jean Pierre, this year's Malaysia project was contracted in July, September and November for Kanthan EP filter changed to bag filter project, Langkawi EP filter changed to bag filter project, Rawang coal mill upgrade project. This is also the best testimony that the Malaysia branch has taken a solid step in the overseas market!

Only 13 Days Taken to Change EP Filter to Bag Filter in Kisen Malaysia Project

(Summary description)2018 is a year of fruitful harvest for the Malaysia project! With the careful preparation of the company's managers and departments, especially the high recognition and full support of the Malaysian Lafarge team headed by Jean Pierre, this year's Malaysia project was contracted in July, September and November for Kanthan EP filter changed to bag filter project, Langkawi EP filter changed to bag filter project, Rawang coal mill upgrade project. This is also the best testimony that the Malaysia branch has taken a solid step in the overseas market!

  • Categories:News
  • Author:
  • Origin:
  • Time of issue:2018-09-15 00:00
  • Views:0
Information

       2018 is a year of fruitful harvest for the Malaysia project! With the careful preparation of the company's managers and departments, especially the high recognition and full support of the Malaysian Lafarge team headed by Jean Pierre, this year's Malaysia project was contracted in July, September and November for Kanthan EP filter changed to bag filter project, Langkawi EP filter changed to bag filter project, Rawang coal mill upgrade project. This is also the best testimony that the Malaysia branch has taken a solid step in the overseas market!

  The kiln of Kanthan EP filter changed to bag filter project was shut down on July 2 and the fan was stopped on July 5. The entire top of the EP, the original fan and the air pipe were removed, and new bag filter,fan and air pipe were installed. The Kisen works was working for 24 hours per day in rotary shifts. And some staff of the project team and Kisen workers worked for 18 hours a day which lasted for half a month. We have overcome the difficulties in dismantling operations, high-altitude operations, large-scale lifting operations that span raw material mills and air ducts, continuous night-time fatigue construction, and tropical hot climate. The trial operation was successfully done at 12 noon on July 21! Lafarge project manager Jean Pierre, site manager Barath, general contracting AAF project manager Chen Dehui, site manager Deng Zhengfan and general contracting engineer went to Nanjing Kaisheng project department to thank! Jean Pierre said: "The Kanthan project has done a good job both in terms of safety and quality, and the progress has exceeded our imagination! Thanks to Nanjing Kaisheng, to the project department, and to all the brothers for their hard work!"

  The kiln of Langkawi EP filter changing to bag filter project was shut down on August 27, and the fan was stopped on the August 29th. After overcoming many difficulties, especially the weather of the rainy season on the island, the project was successfully tested on the afternoon of September 10th! It took only 13 days to stop the system fan, remove the top of the electric dust collector, remove the fan of the air duct, and install a new bag filter and fan air duct. Finally, it took only 13 days to trial run the fan and the system. The progress made a record for the speed of Lafarge's EP filter changed to bag filter! This project is the first time for Kisen to enter the Langkawi plant. But we have won the high praise and recognition from this plant with our strength!

  We won’t forget our original intentions and will keep moving forward! In 2018, our Malaysia projects are embracing safety. We are smiling with quality, and racing against time! We are in the Pacific South China Coast, abide by the image of the people, inherit the national culture, and carry forward the entrepreneurial spirit! Honest and trustworthy, hard-working! We will make persistent efforts and live up to our mission! The Malaysia Rawang project is also the finale of 2018. Our project will pay more attention, take actions and keep improving. We are determined to become the model project of the company's technological upgrade project! We will also unite our ambitions to ensure a "harvest year".

Home page     |     About kisen     |     Company news     |     Main business     |     Results show     |     Contact us

Address: 13 / F, Block D, 303 Hanzhongmen Street, Nanjing   Tel:+86-25-68178768   Fax:+86-25-86219769

Mail: kisen@kisen.net

苏ICP备12007421号-2. All Rights Reserved             WEBSITE CONSTRUCTION:GROW FORCE  Nanjing